Short Network

Short Network

Short network is the "main artery" connecting the transformer secondary to the electrodes, a critical high-current circuit unique to Electric Arc Furnaces (EAF), Ladle Furnaces (LF), Submerged Arc Furnaces (SAF), and other metallurgical furnaces.
Send Inquiry
Description
Technical Parameters

Short network is the "main artery" connecting the transformer secondary to the electrodes, a critical high-current circuit unique to Electric Arc Furnaces (EAF), Ladle Furnaces (LF), Submerged Arc Furnaces (SAF), and other metallurgical furnaces.

 

Its typical characteristics include:

  • Extremely high current (up to tens or even hundreds of kiloamperes)
  • Low voltage (only tens to a few hundred volts)
  • Short physical length (typically less than 20 meters for large furnaces)

 

The performance of the short network is a core indicator of the furnace's technical and economic efficiency. Its design and operational condition directly influence:

  • Furnace productivity
  • Refractory lining service life
  • Electrical efficiency
  • Power factor
Short network (bus systems)

 

Key Selection Parameters

 

When selecting a short network, the following technical parameters should be carefully considered:

1. Transformer and Furnace Parameters

  • Rated secondary current and voltage of the transformer (fundamental basis for selecting conductor cross-section)
  • Furnace type and nominal capacity
  • Distribution circle diameter of the three-phase electrodes and electrode diameter

 

2. Interface and Installation Dimensions

  • Specifications of conductor connectors, such as flexible compensators, busbars, and water-cooled cable connections
  • Cooling water pipeline interface dimensions to ensure compatibility with on-site piping
  • Original drawings or existing components are recommended for reference

 

3. Electrical Performance and Insulation Requirements

  • Three-phase impedance balance requirements (typically imbalance ≤ 5%)
  • System insulation level and method
  • Insulation materials between electrode holders and conductor arms
Electric Arc Furnace Short Network

 

Ordering and Acceptance Considerations

1.Define Scope of Supply and Delivery Schedule

  • Specify whether the supply includes only the core conductors or additional components such as mounting brackets
  • Confirm delivery, installation, and commissioning timelines

 

2.Clarify Installation and Commissioning Responsibilities

  • Clearly assign responsibilities for installation and commissioning in the contract

 

3.Specify Acceptance Standards

  • Follow national standards or industry norms
  • Core performance indicators such as impedance balance should be clearly defined with acceptance methods

 

4. Short Network After-Sales Service and Warranty

  • Warranty for key components (e.g., critical welds, insulation parts)
  • Response times for after-sales service during the warranty period

 

LF Short Network

 

Send Message